WE
ARE PROVIDING CASE STUDY ANSWERS
ASSIGNMENT
SOLUTIONS, PROJECT REPORTS
AND
THESIS
ISBM / IIBMS / IIBM / ISMS / KSBM / NIPM -
SMU / SYMBIOSIS / XAVIER / NIRM / NAMS….
MBA EMBA
BMS GDM MIS
MIB
DMS
MMS DBM PGDMA
DBA…..
WEBSITE: www.casestudies.co.in
ARAVIND 09901366442 09902787224
Case 1
Disaster Recovery at Marshall
Field’s (Another Chicago River Story)
Early in the morning
on April 13, 1992, basements in Chicago ’s
downtown central business district began to flood. A hole the size of an
automobile had developed between the river and an adjacent abandoned tunnel.
The tunnel, built in the early 1900s for transporting coal, runs throughout the
downtown area. When the tunnel flooded, so did the basements connected to it,
some 272 in all, including that of major retailer Marshall Field’s.
The
problem was first noted at 5:30 A.M. by a member of the Marshall Field’s
trouble desk who saw water pouring into the basement. The manager of
maintenance was notified and immediately took charge. His first actions were to
contact the Chicago Fire and Water Departments, and Marshall Field’s parent
company, Dayton Hudson in Minneapolis .
Electricity—and with it all elevator, computer, communication, and security
services for the 15-story building—would soon be lost. The building was
evacuated and elevators were moved above basement levels. A command post was
quickly established and a team formed from various departments such as
facilities, security, human resources, public relations, and financial, legal,
insurance, and support services. Later that day, members of Dayton Hudson’s
risk management group arrived from Minneapolis
to take over coordinating the team’s efforts. The team initially met twice a
week to evaluate progress as the store recovered. The goal of the team was to
ensure the safety of employees and customers, minimize flood damage, and resume
normal operations as soon as possible. The team hoped to open the store to
customers 1 week after the flood began.
An
attempt was made to pump out the water; however, as long as the tunnel hole
remained unrepaired, the Chicago River continued to pour into the basements.
Thus, the basements remained flooded until the tunnel was sealed and the Army
Corps of Engineers could give approval to start pumping. Everything in the
second-level basement was a loss, including equipment for security, heating,
ventilation, air-conditioning, fire sprinkling, and mechanical services. Most
merchandise in the first-level basement stockrooms also was lost.
Electricians
worked around the clock to install emergency generators and restore lighting
and elevator service. Additional security officers were hired. An emergency
pumping system and new piping to the water sprinkling tank were installed so
the sprinkler system could be reactivated. Measures were taken to monitor ventilation
and air quality and dehumidifiers and fans were installed to improve air
quality. Within the week, inspectors from the City of Chicago and OSHA gave approval to reopen the
store.
During
this time, engineers had repaired the hole in the tunnel. After water was
drained from the Marshall Field’s basements, damaged merchandise was removed
and sold to a salvager. The second basement had to be gutted to assure removal
of contaminants. Salvageable machinery had to be disassembled and sanitized.
The
extent of the damage was assessed and insurance claims filed. A construction
company was hired to manage restoration of the damaged areas. Throughout the
ordeal, the public relations department dealt with the media, being candid yet
showing confidence in the recovery effort. Customers had to be assured that the
store was safe and employees kept apprised of the recovery effort.
This
case illustrates crisis management, an important aspect of which is having a
team that moves fast to minimize losses and quickly recover damages. At the
beginning of a disaster there is little time to plan, though companies and
public agencies often have crisis guidelines for responding to emergency
situations. Afterwards they then develop more specific, detailed plans to guide
longer-term recovery efforts.
QUESTIONS
1. In what ways are the
Marshall Field’s flood disaster recovery effort a project? Why are large-scale
disaster response and recovery efforts projects?
2. In what ways do the
characteristics of crisis management as described in this case correspond to
those of project management?
3. Who was (were) the
project manager(s) and what was his or her (their) responsibility? Who was
assigned to the project team and why were they on the team?
4. Comment on the
appropriateness of using disaster recovery efforts such as this.
5. What form of project
management (basic, program, and so on) does this case most closely resemble?
Case 2 Flexible Benefits System
Implementation at Quick Medical Center
The management committee of Quick Medical
Center wanted to reduce
the cost and improve the value and service of its employee benefits coverage.
To accomplish this it decided to procure and implement a new benefits system.
The new system would have no meet four goal; improved responsiveness to
employee needs, added benefits flexibility, better cost management, and greater
coordination of human resource objectives with business strategies. A
multifunctional team of 13 members was formed by selecting representatives of
departments at Quick that would rely most on the new system—Human Resources
(HR), Financial Systems (FS), and Information Services (IS). Representation
from each department was important to assuring all departmental needs would be
met. The team also included six technical experts from the software consulting
firm of Hun and Bar Software (HBS).
Early
in the project a workshop was held with team members from Quick and HBS to
clarify and finalize project objectives and develop a project plan, milestones,
and schedules. Project completion was set at 10 months. In that time HBS had to
develop and supply all hardware and software for the new system; the system had
to be brought on-line, tested, and approved; HR workers had to be trained how
to operate the system and load existing employee data; all Quick employees had
to be educated about and enrolled in the new benefits process; and the
enrollment data had to be entered in the system.
The
director of FS was chosen to oversee the project. She had a technical
background and, prior to serving as director, had worked in the IS group where
she assisted in implementing Quick’s patient care information system. Everyone
on the team approved of her appointment as project leader, and many team
members had worked with her previously. Two team members had worked with her
previously. Two team leaders were also selected, one each from HR and IS. The
HR leader’s task was to ensure that the new system met HR requirements and the
needs of Quick employees, and the IS leader’s task was to ensure that the new
software interfaced with other Quick systems.
Members
of the Quick team were committed to the project on a part-time basis. Roughly
50 percent of the time they worked on the project; the rest of the time they
performed their normal daily duties. The project manager and team leaders also
worked on the project part-time. When conflicts arose, the project took
priority. Given specific performance requirements and time deadlines, the Quick
top management committee made it clear that successful project completion was imperative.
The project manager was given authority over functional managers and project
team members regarding all project related decisions.
QUESTIONS
1. What form of project
management (basic, program, and so on) does this case most closely resemble?
2. The project manager
is also the director of FS, only one of the departments that will be affected
by the new benefits system. Does this seem like a good idea? What are the pros
and cons of her selection?
3. Comment on the team
members’ part time assignment to the project and the expectation that they give
the project top priority.
4. Much of the success
of this project depends on the performance of team members who are not employed
by Quick, namely the HBS consultants. They must develop the entire
hardware/software benefits system. Why was an outside firm likely chosen for
such an important part of the project manager in meeting project goals?
Case 3
Glades County Sanitary District
Glades Country is a region on the Gulf Coast
with a population of 600,000. About 90 percent of the population is located in
and near the city of Sitkus .
The main attractions of the area are its clean, sandy beaches and nearby
fishing. Resorts, restaurants, hotels, retailers, and the Sitkus/Glades County
economy in general rely on these attractions for tourist dollars.
In
the last decade, Glades Country has experienced a near doubling of population
and industry. One result has been the noticeable increase in the level of water
pollution along the coast due primarily to the increased raw sewage dumped by Glades County
into the Gulf. Ordinarily, the Glades
County sewer system
directs effluent waste through filtration plants before pumping it into the
Gulf. Although the Glades County Sanitary District (GCSD) usually is able to
handle the county’s sewage, during heavy rains the runoff from paved surfaces
exceeds sewer capacity and must be diverted past filtration plants, directly in
to the Gulf. Following heavy rains, the beaches are cluttered with dead fish
and debris. The Gulf fishing trade also is affected; pollution drives away
desirable fish. Recently, the water pollution level has become high enough to
damage both the tourist and fishing trade. Besides coastal pollution, there is
also concern that as the population continues to increase, the county’s primary
fresh water source, Glades
River , will also become
polluted.
The
GCSD has been mandated to prepare a comprehensive water waste management
program that will reverse the trend in pollution along the Gulf Coast
as well as handle the expected increase in effluent wastes over the next 20
years. Although not yet specified, it is known that the program will include
new sewers, filtration plants, and stricter anti-pollution laws. As a first
step, GCSD must establish the overall direction and mission of the program.
Wherever
possible, answer the following questions (given the limited information, it is
okay to advance some logical guesses; if you are not able to answer a question
for lack of information, indicate how and where, as a systems analyst, you
would get it):
Questions:
1. What is the system?
What are its key elements and subsystems? What are the boundaries and how are
they determined? What is the environment?
2. Who are the decision
makers?
3. What is the problem?
Carefully formulate it.
4. Define the overall
objective of the water waste management program. Because the program is
wide-ranging in scope, you should break this down into several sub- objectives.
5. Define the criteria
or measures of performance to be used to determine whether the objectives of
the program are being met. Specify several criteria for each sub-objective. As
much as possible, the criteria should be quantitative, although some
qualitative measures should also be included. How will you know if the criteria
that you define are the appropriate ones to use?
6. What are the
resources and constraints?
7. Elaborate on the
kinds of alternatives and range of solutions to solving the problem.
8. Discuss some
techniques that could be used to help evaluate which alternatives are best.
Case 4 West Coast University
Medical
center
(This is a true story.) West Coast University
Medical Center
(Pseudonym) is a large university teaching and research hospital with a
national reputation for excellence in health care practice, education, and
research. Always seeking to sustain that reputation, the senior executive board
at the Medical Center (WCMC) decided to install a comprehensive medical
diagnostic system. The system would be linked to WCMC’s computer servers and be
available to physicians via the computer network. Because every physician’s
office at WCMC has a PC, doctors and staff could access the system from these
offices as well as from their homes or private-practice offices. By simply
clicking icons to access a medical specialty area, then keying in answers to
queries about a patient’s symptoms, medical history, and so on, a physician
could get a list of diagnostics with associated statistics.
The
senior board sent a questionnaire to manager in every department about needs in
their areas and how they felt the system might improve doctor’s performances.
Most managers felt it would save the doctor’s time and improve their
performances. The hospital computing and information systems (CIS) group was
assigned to investigate the cost and feasibility of implementing the system.
CIS staff interviewed medical-center managers and software vendors specializing
in diagnostic systems. The study showed high enthusiasm among the respondents
and a long list of potential benefits. Based on the study report, the senior
board approved the system.
The
CIS manager contacted three well-known consulting firms that specialized in
medical diagnostic systems and invited each to give a presentation. Based on
the presentations, he chose one firm to assist the CIS group in identifying,
selecting, and integrating several software packages into a single, complete
diagnostic system.
One
year and several million dollars later the project was completed. However,
within a year of its completion it was clear that the system had failed.
Although it did everything the consultants and software vendors had promised,
the few doctors that did access it complained that many of the system
“benefits” were irrelevant, and that certain features they desired were lacking.
QUESTIONS
1. Why was the system a
failure?
2. What was the likely
cause of its lack of use?
3. What steps or
procedures were absent or poorly handled in the project conception phase?
Case 5 X-philes Data Management
Corporation
X-philes Data Management Corporation (XDM)
requires assistance in tow large projects it is about to undertake: Agentfox
and Mulder. Although the projects are comparable in terms of size, technical
requirements, and estimated completion time, they are independent and will have
their own project managers and teams. Work for both projects is to be
contracted to outside consultants.
Two
managers at XDM, one assigned each to Agentfox and Mulder, prepare RFPs and
send them to several contractors. The RFP for Agentfox includes a statement of
work that specifies system performance and quality requirements, a desired
completion deadline, and contract conditions. As an incentive, the contractor
will receive a bonus for exceeding minimal quality measures and completing the
project early, and will be charged a penalty for poor quality and late
completion. The project will be tracked using precise quality measures, and the
contractor will have to submit detailed monthly status reports. The REP for
Mulder simply includes a statement of the type of work to be done, an expected
budget limit, and the desired completion date.
Based
on proposals received in response to the REPs, the managers responsible for
Mulder and Agentfox each select a contractor. Unknown to either manager is that
they select the same contractor, Yrisket Systems. Yrisket is selected for the
Mulder project because its specified price is somewhat less than the budget
limit in the REP, and Yrisket has a good reputation in the business. Yrisket is
chosen for the Agentfox contract for similar reasons—good price and good
reputation. In responding to the Agentfox REP, Yrisket managers had to work
hard to get the price down to the amount specified, but they felt that by doing
quality work on the project they could make a tidy profit through the incentive
offered.
A
few months after the projects are underway, some of Yrisket’s key employees
quit their jobs. Thus, to meet their commitments to both projects, Yrisket
workers have to work long hours and weekends. It is apparent, however, that
these extra efforts might not be enough, especially because Yrisket has a
contract with another customer and will have to start a third project in the
near future.
QUESTIONS
1. What do you think
will happen?
2. How do you think the
crisis facing Yrisket will affect the Mulder project? The Agentfox project?
Case 6 Star-Board Construction/West-Starr
Associates
Star-Board Construction (SBC) is the prime
contractor for Gargantuan Project, a large skyscraper project in downtown Manhattan . SBC is working
directly from drawings received from the architect, West-Starr Associates
(WSA). Robert Starr, owner and chief architect of WSA, had designed similar
buildings and viewed this one as similar to the others. However, one difference
between this building and the others is in its facing, which consists of very
large granite slabs—slabs much larger than traditionally used and larger than
anything with which either WSA or SBC has had prior experience.
Halfway
into project, Kent Star, owner and project manager for SBC, started to receive
reports from his site superintendent about recurring problems with window
installation. The windows are factory units, premanufactured according to WSA’s
specifications. Plans are to install the granite facing on the building
according to specifications that allow for dimensional variations in the window
units. The architect provided the specification
that a ½-inch tolerance for each window space be made (that is, the
window space between granite slabs could vary as much as ¼ inch larger or
smaller than the specified value). This created a problem for the construction
crew that found the granite slabs too huge to install with such precision. As a
result, the spacing between slabs is often too small, making it difficult or
impossible to install window units. Most of the 2,000 window units for the
building have already been manufactured so it is too late to change their
specifications, and most of the granite slabs have been hung on the building. The
only recourse for making window units fit into tight spaces would be to grind
away or reinstall the granite. It is going to be very expensive and will
certainly delay completion of the building.
QUESTION
1. What steps or
actions should the architect and contractor have taken before committing to the
specifications on the window units and spacing between granite slabs the would
have reduced or eliminated this problem?
No comments:
Post a Comment